Question: Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days. Activity Immediate Predecessor Normal Time Crash Time Normal Cost

Below are the data for a Time-Cost CPM Scheduling

Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days. Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A None 4 3 192 398 A 4 3 297 595 A 1 1 246 185 D B and C 5 4 504 546 E D 4 2 499 897 If you crash this project to reduce the total time by one day (keeping the cost as low as possible), what is the total cost of the project? Please give your answer in $. Round answer to 0 decimal places, if applicable Your