Question: Below are the data for Sample Project for CPM Analysis. Activity Predecessor Duration (Days A 2 B 6 C 4 D A 3 E C

Below are the data for Sample Project for CPM Analysis.

Activity Predecessor Duration (Days

A 2

B 6

C 4

D A 3

E C 5

F A 4

G B, D, E 2

  1. Draw the network model to show the sequence of the project activities and identify the critical path (Activities on the critical path) and the number of days required to complete the project.
  2. Compute the slack time (in days) for each activity