Question: Exercises on PERT CPM: Draw and diagram, compute the ECT, CPM Find the Total Slack. begin{tabular}{|l|l|l|l|l|l|} hline Activity & Predecessor & Duration(DAYS) & Activity &

Exercises on PERT CPM: Draw and diagram, compute the ECT, CPM Find the Total Slack. \begin{tabular}{|l|l|l|l|l|l|} \hline Activity & Predecessor & Duration(DAYS) & Activity & Predecessor & Duration (Days ) \\ \hline A & NONE & 10 & F & D C & 2 \\ \hline B & NONE & 2 & G & E & 1 \\ \hline C & AB & 5 & H & E & 4 \\ \hline D & NONE & 6 & I & F G & 6 \\ \hline E & D C & 8 & J & H I & 5 \\ \hline \end{tabular} \begin{tabular}{|l|l|l|l|l|l|} \hline Activity & Predecegsor & Duration(DAYS) & Activity & Predecessor & Duration (Days) \\ \hline A & NONE & 5 & F & D E & 7 \\ \hline B & A & 1 & G & E D & 4 \\ \hline C & NONE & 11 & H & F & 6 \\ \hline D & A & 12 & I & H G & 1 \\ \hline E & C B & 5 & J & I & 3 \\ \hline \end{tabular}