Question: Table EX 1 3 . 5 shows the precedence relationships among the activities to complete a project. Table EX 1 3 . 5 Activity Predecessor

Table EX 13.5 shows the precedence relationships among the activities to complete a
project.
Table EX 13.5
Activity Predecessor Duration (Days)
A 18
B A 19
C A 17
D B 15
E C 1