Question: Below is data for a project. (in months) If there was delay and activity Factually took 9 months, then how many months will it take

 Below is data for a project. (in months) If there was

Below is data for a project. (in months) If there was delay and activity Factually took 9 months, then how many months will it take to complete this project? activity duration (months) predecessor > 0 0 W 00u 0 m B, C A Na 0 D, E I F,G