Question: Budget Assignment Introduction and Instructions: You are a Project Manager for Seneca Apps g and you are making a project budget to present it to

Budget Assignment Introduction and Instructions: You are a Project Manager for Seneca Apps g and you are making a project budget to present it to the Senior Management Team. Use the following table and WBS template for this assignment: Customized Connecting Software . . Preceding Activity Time (Work A t t C y Weeks) 1 Connecting Software Project for Mrs. Y None 2 Requirement Collection None 10 3 Resource Allocation 2 4 4 Hardware Specification 2 4 5 Software Build 3 10 5 Unit Testing 4 2 7 IPR Filing 3, 9 1 8 System Testing 6 2 9 End to End Testing 5 5 10 Project Handover 7, 9 4 11 END (Milestone) 10 0 Customized Connecting Software Requirement Resource Hardware and End of Testin Project Collection Allocation Software Built g Handover