Question: Building a house Activity Name Activity Description Activity Predecessor Activity Duration (Months) A Design house and obtain financing Lay foundation Order and receive materials Build

Building a house Activity Name Activity

Building a house Activity Name Activity Description Activity Predecessor Activity Duration (Months) A Design house and obtain financing Lay foundation Order and receive materials Build house B,C B, C Select paint Select carpet Finish work D, E, F B. Identify the critical path. Use Linear Programming and provide your model formulation in your answer. You can solve your model either in Excel or LINDO. C. Based on model solution, (part B), determine the project duration time