Question: ( c ) [ 1 0 ] The project is ready to begin now, and the deadline for completion is 1 0 0 weeks. What

(c)[10] The project is ready to begin now, and the deadline for completion is 100 weeks. What duration should the project manager plan for in order to have a 95% likelihood of completing the project by the deadline? Note: If this planning date is less than the expected project duration, you may assume that activities may be crashed (e.g. durations reduced) with no change in the activity variance.
ANSWER: 0.95=Ptp-100=(1.65)=((100-tp)??e22)=((100-tp)1.672+5.672+322)
1.65=(100-tp)1.672+5.672+322=>tp=(-1.65**6.625)+100=89.1 weeks
Dr. L. Dale Thomas
April 4,2024
 (c)[10] The project is ready to begin now, and the deadline

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!