Question: Consider the following project task information, where all durations are given in weeks. Activity Preceded by Expected Duration Standard Deviation Variance A - - 3

Consider the following project task information, where all durations are given in weeks.
Activity Preceded by
Expected
Duration
Standard
Deviation Variance
A --321.331.78
B --27.671.672.78
C A 363.3311.11
D B 160.670.44
E B 3200
F B 53.675.6732.11
G D 16.6724
H E,G 20.331.672.78
I E,G 342.677.11
J C,F,H 17.6739
(a)[5] You have determined that the critical path is B-F-J. Determine the expected project
duration (in weeks).
ANSWER: ______________________
(b)[10] Determine the project duration (in weeks) for which you can be 99% certain that the
project will be completed.
ANSWER: _____________________
(c)[10] The project is ready to begin now, and the deadline for completion is 100 weeks.
What duration should the project manager plan for in order to have a 95% likelihood of
completing the project by the deadline? Note:
If this planning date is less than the expected
project duration, you may assume that activities may be crashed (e.g. durations reduced)
with no change in the activity variance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!