Question: Consider the following project task information, where all durations are given in weeks. Activity Preceded by Expected Duration Standard Deviation Variance A - - 3
Consider the following project task information, where all durations are given in weeks.
Activity Preceded by
Expected
Duration
Standard
Deviation Variance
A
B
C A
D B
E B
F B
G D
H EG
I EG
J CFH
a You have determined that the critical path is BFJ Determine the expected project
duration in weeks
ANSWER:
b Determine the project duration in weeks for which you can be certain that the
project will be completed.
ANSWER:
c The project is ready to begin now, and the deadline for completion is weeks.
What duration should the project manager plan for in order to have a likelihood of
completing the project by the deadline? Note:
If this planning date is less than the expected
project duration, you may assume that activities may be crashed eg durations reduced
with no change in the activity variance.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock