Question: Calculate CPM Activity Immediate Predecessors Duration A 0 2 B A 2 C A 1 E A 6 I C,E 1 H B 1 D

Calculate CPM

Activity Immediate Predecessors Duration
A 0 2
B A 2
C A 1
E A 6
I C,E 1
H B 1
D B 1
F B 3
G B 1
J I 1
K J 1
L K 1
M L 1
N H,D,F,G,M 4