Question: Calculate Critical Path for the below project using PERT calculation: Activity Durations (weeks) Predecessor A 10 - B 20 A C 5 B D 10

Calculate Critical Path for the below project using PERT calculation:

Activity

Durations (weeks)

Predecessor

A

10

-

B

20

A

C

5

B

D

10

C

E

2

C

F

4

B

G

2

D,E

H

2

G