Question: Calculate Critical Path for the below project using PERT calculation: Activity Durations (weeks) Predecessor A 10 - B 20 A C 5 B D 10
Calculate Critical Path for the below project using PERT calculation:
| Activity | Durations (weeks) | Predecessor |
| A | 10 | - |
| B | 20 | A |
| C | 5 | B |
| D | 10 | C |
| E | 2 | C |
| F | 4 | B |
| G | 2 | D,E |
| H | 2 | G |
|
|
|
|