Question: Calculate the expected duration for the following tasks. (b) Draw the CPM Chart using the critical path method. (c) Identify all of the paths and

Calculate the expected duration for the following tasks. (b) Draw the CPM Chart using the critical path method. (c) Identify all of the paths and select the critical path. (d) How much total slack do we have in the system? (15 pts)

Act Predecessor Optimistic Estimate Most Likely Estimate Pessimistic Estimate Expected Duration

A 1 2 4

B A 3 5 8

C B 2 4 5

D B 2 3 6

E B 1 1 1

F C,D 2 4 6

G D,E 2 3 4

H F,G 1 2 5

I G 4 5 9

J HI .5 1 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!