Question: calculate the probability that the project will be completed in 40 weeks calculate the probability that the project will be completed in 44 weeks Optimistic

calculate the probability that the project will be completed in 40 weeks
calculate the probability that the project will be completed in 44 weeks
calculate the probability that the project will
Optimistic Time (O.T.) Mostly Likely Time (M.T.) Pessimistic Time (P.T.) Immediate Activity Predecessor 7 A B None A 5 3 10 7 5 A 4 7 12 D B 4 5 8 9 10 15 E F. D 4 4 5 G D, E 3 6 8 H F 6 10 5 5 1 G 8 11 J HI 3 3 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image