Question: Callers are helped in a process with two sequential resources . The capacities of the resources are 2 . 8 and 4 . 3 callers

Callers are helped in a process with two sequential resources . The capacities of the resources are 2.8 and 4.3 callers per minute What is the capacity of this process in terms of callers per minute ?