Question: Can this be solved in Excel? The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time A
Can this be solved in Excel?
The following represents a project with known activity times. All times are in weeks.
| Activity | Immediate Predecessor | Time |
| A | - | 6 |
| B | - | 3 |
| C | A | 5 |
| D | - | 2 |
| E | C | 4 |
| F | D | 3 |
| G | B, C | 2 |
| H | G | 3 |
| I | F, G | 5 |
| J | H | 4 |
| K | E, H | 2 |
| L | K | 3 |
- Create a CPM Network. (15 pts)
- What is the projects expected completion date? (5 pts)
- What activities are on the critical path? (10 pts)
- Compute the slack time for all non-critical activities. (15 pts)
- What is the latest possible start time for activity E? (5 pts)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock