Question: can you please calculate the slack time for each activity Activity Activity Time (days) ABCDEFG 8533538 Immediate Predecessor(s) A A B, C D E E
can you please calculate the slack time for each activity
Activity Activity Time (days) ABCDEFG 8533538 Immediate Predecessor(s) A A B, C D E E a. Choose the corect network diagram for this project pos O OC 9 Stan b. Determine the critical path and project duration The critical path is path A-B-D-E-G and the project duration is 29 days (Enter your response as an integer) Calculate the sack for each activity (Enter your responses as integers) Finish 680 Activity A