Question: CASE STUDY Your firm MS Ankomadu has won a project of 1,785,000 to build a 161kV/33kV sub-station. You have been selected as the project manager

CASE STUDY

Your firm MS Ankomadu has won a project of 1,785,000 to build a

161kV/33kV sub-station. You have been selected as the project manager to lead

the project team for the successful execution of the project.

You are the project manager, there are a total of 8,400 hours of work schedule

on the project. You made your checks with the accounting department, and they

told you that you have spent a total of 1,144,000. According to the schedule,

your team should have worked 5000 hours, but your foreman says that the team

was allowed to work some overtime, and they have actually put in 5000 hours

of work.

Base on the CASE STUDY calculate the following Earned Value

numbers and write their full meaning of the following: - PV, EV, CV,

BAC, AC, SV, SPI, and CPI.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!