Question: Case Study: Your firm MS MACKAY LTD. won a project of 1,785,000 to build a 161kV/33kV sub-station. You have been selected as the project manager
Case Study:
Your firm MS MACKAY LTD. won a project of 1,785,000 to build a 161kV/33kV sub-station. You have been selected as the project manager to lead the project team for the successful execution of the project. You are the project manager, there are a total of 8,400 hours of work schedule on the project. You made your checks with the accounting department, and they told you that you have spent a total of 1,144,000. According to the schedule, your team should have worked 5000 hours, but your foreman says that the team was allowed to work some overtime, and they have actually put in 5600 hours of work.
a. Produce the works breakdown structure (WBS) for the project in the CASE STUDY.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts