Question: Chapter 3, Question 7, part a: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

Chapter 3, Question 7, part a: Task time
Chapter 3, Question 7, part a: Task time
Chapter 3, Question 7, part a: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: (a) Draw the project network using AON. (b) Identify the critical path. (c) What is the expected project length? (d) Draw a Gantt chart for the project. An AOA network is needed for this question None of the above