Question: Clear my choice A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(7.5,

Clear my choice A project has four major

Clear my choice A project has four major activities. Activity A precedes activity B, activity C precedes activity D. 3-point estimates for activities are A(7.5, 15, 22.5), B( 7, 14, 21), C( 1, 2, 3), D( 13.5, 27, 40.5) weeks. What probability would you assign to a project duration of more than 29 weeks? O a. 0.75 O b. 0.139 O c. 0.5 O d. 0.723