Question: Clients are served in a process with two resources. A worker in the first resource serves 7.3 clients per hour and a worker in the

Clients are served in a process with two resources. A worker in the first resource serves 7.3 clients per hour and a worker in the second resource serves 2 clients per hour. The first resource has 1 worker and the second resource has 3 workers.

What is the capacity of this process in terms of clients per hour?