Question: People are served in a process with two resources. A worker in the first resource serves 20 people per hour and a worker in the

People are served in a process with two resources. A worker in the first resource serves 20 people per hour and a worker in the second resource serves 14 people per hour. The first resource has 6 workers and the second resource has 8 workers. Demand occurs at the rate 1.9 people per minute.

What is the implied utilization (%) of the second resource?