Clients are served in a process with two resources. The processing time of the first resource is 11 hours. The processing time of the second resource is 12 hours. The first resource has 4 workers and the second resource has 3 workers. The cycle time of the process is 18 hours. What is the average labor utilization (\%)? Note: Round your answer to 1 decimal place