Question: From the project plan, we that a project has a total budgeted cost of $877,748 and a project completion time of 15 weeks. At the

From the project plan, we that a project has a
From the project plan, we that a project has a total budgeted cost of $877,748 and a project completion time of 15 weeks. At the moment, the project has been in a performing stage. At the end of week 8 , the project progress report shows that the project has consumed a total of $327,701, the project cumulative earned value is $354,356, and the project schedule performance index is 0.92. What is the estimated project cost at completion if the project continues at the cost performance index of 1.0 ? Use at least 4 decimals