Question: From the project plan, we that a project has a total budgeted cost of $595,070 and a project completion time of 15 weeks. At the

From the project plan, we that a project has a
From the project plan, we that a project has a total budgeted cost of $595,070 and a project completion time of 15 weeks. At the moment, the project has been in a performing phase. At the end of week 8, the project progress report shows that the project has consumed a total of $238,391, the project schedule variance is $41,001 and the project schedule variance is $32,602. What is the estimated project cost at completion if the project continues at the cost performance index observed at the end of week 8 ? Use at least 4 decimals