Question: Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office

Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The activities that would have to be completed before beginning construction are listed below.

Activity

Description

Immediate

Predecessors

Time

(weeks)

A

Survey building site

-

6

B

Develop initial design

-

8

C

Obtain board approval

A, B

12

D

Select architect

C

4

E

Establish budge

C

6

F

Finalize design

D, E

15

G

Obtain financing

E

12

H

Hire contractor

F. G

8

Required:

a. Develop a network for this project. (8 marks)

b. Identify the critical path (include EST. EFT, LST, LFT and the Slack Variable). (12 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!