Question: Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office
Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The activities that would have to be completed before beginning construction are listed below.
| Activity | Description | Immediate Predecessors | Time (weeks) |
| A | Survey building site | - | 6 |
| B | Develop initial design | - | 8 |
| C | Obtain board approval | A, B | 12 |
| D | Select architect | C | 4 |
| E | Establish budge | C | 6 |
| F | Finalize design | D, E | 15 |
| G | Obtain financing | E | 12 |
| H | Hire contractor | F. G | 8 |
Required:
a. Develop a network for this project. (8 marks)
b. Identify the critical path (include EST. EFT, LST, LFT and the Slack Variable). (12 marks)