Question: Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office
Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The activities that would have to be completed before beginning construction are listed below. 
a. Develop a network for this project. b. Identify the critical path(s). c. Construct an early-state date Gantt chart. d. Does it appear reasonable that construction could begin one year after the decision to begin the project? What is the project completion time