Question: Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office
-
Colonial State College is considering building a new athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The activities that would have to be completed before beginning construction are listed next.
| Activity | Description | Immediate Predecessors | Time (weeks) |
| A | Survey building site | ------ | 6 |
| B | Develop initial design | ------ | 8 |
| C | Obtain board approval | A,B | 12 |
| D | Select architect | C | 4 |
| E | Establish budget | C | 6 |
| F | Finalize design | D,E | 15 |
| G | Obtain financing | E | 12 |
| H | Hire contractor | F,G | 8 |
-
Develop a network for this project using the AON method.
-
Analyze the project network to determine the ET, EF, LS, and LF for each activity. Identify the critical paths.
-
Does it appear reasonable that construction could begin 1 year after the decision to begin the project? What is the project-completion time?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
