Question: Colson Corp. has planned a simple project having four tasks. The task information for the project is shown below. What is the estimated project duration?
Colson Corp. has planned a simple project having four tasks. The task information for the project is shown below. What is the estimated project duration? Enter the total number of days needed to complete the project
Task Estimated Duration Immediate Predecessors
A days None
B days A
C days A
D days B C
Group of answer choices
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
