Question: Colson Corp. has planned a simple project having four tasks. The task information for the project is shown below. What is the estimated project duration?

Colson Corp. has planned a simple project having four tasks. The task information for the project is shown below. What is the estimated project duration? (Enter the total number of days needed to complete the project)
Task Estimated Duration Immediate Predecessors
A 6 days None
B 5 days A
C 4 days A
D 3 days B, C
Group of answer choices
18
21
15
12
14
13