Question: Colson Corporation has planned a simple project with four tasks. The task information for the project is shown below: Task Estimated Duration Immediate Predecessors A
Colson Corporation has planned a simple project with four tasks. The task information for the project is shown below:
Task Estimated Duration Immediate Predecessors
A days None
B days A
C days A
D days BC
Does any task have slack? If so how much?
Multiple Choice
None of the tasks have slack.
Task C has three days of slack.
Task C has four days of slack.
Task B has three days of slack.
Task D has two days of slack.
PrevQuestion of Total of Visit question mapNext
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
