Question: Colson Corporation has planned a simple project with four tasks. The task information for the project is shown below: Task Estimated Duration Immediate Predecessors A

Colson Corporation has planned a simple project with four tasks. The task information for the project is shown below:
Task Estimated Duration Immediate Predecessors
A 10 days None
B 7 days A
C 4 days A
D 8 days B,C
Does any task have slack? If so, how much?
Multiple Choice
None of the tasks have slack.
Task C has three days of slack.
Task C has four days of slack.
Task B has three days of slack.
Task D has two days of slack.