Question: Colson Corporation has planned a simple project with four tasks. The task information for the project is shown below: Task Estimated Duration Immediate Predecessors A

Colson Corporation has planned a simple project with four tasks. The task information for the project is shown below:
Task Estimated Duration Immediate Predecessors
A 10 days None
B 7 days A
C 4 days A
D 8 days B,C
What is the estimated completion time for the project?
Group of answer choices
22 days
25 days
19 days
29 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!