Question: table [ [ Task , Estimated Duration,Immediate ] , [ Predecessors , , ] , [ B , 1 0 days,None ] , [

\table[[Task,Estimated Duration,Immediate],[Predecessors,,],[B,10 days,None],[C,7 days,A],[D,4 days,A]]
Slack =LF-EF
Slack =LS-ES
ES=max{EFpreceding}
EF=ES+ Activity
LF=min{LSsucceeding}
LS=LF- Activity
Colson Corp. has planned a simple project having four tasks. The task information for the project is shown above. Does any task h slack? If so, how much?
None of the tasks have slack
Task B has 3 days of slack
 \table[[Task,Estimated Duration,Immediate],[Predecessors,,],[B,10 days,None],[C,7 days,A],[D,4 days,A]] Slack =LF-EF Slack =LS-ES ES=max{EFpreceding} EF=ES+