Question: Complete the following question relating to the data given for the precedence diagram. table [ [ ACTIVITY , PRECEDED BY , DURATION ( WEEKS

Complete the following question relating to the data given for the precedence diagram.
\table[[ACTIVITY,PRECEDED BY,DURATION(WEEKS)],[C,-,6],[D,-,2],[E,C.D,1],[F,C.D,6],[G,C.D,3],[H,E.F,3]]
Calculate and present the values for Activity C only
Prompts
Early Start of Act C
Early Finish of Act F
Latest Finish of Act G
Latest Start of Act E
(5) Float of Act G
Answers
Select match
Select match
Select match
Select match
Select match