Question: Complete the table and determine whether the task is behind or ahead of schedule, over or under budget. Task AC EV PV SV SPI Analysis

Complete the table and determine whether the task
Complete the table and determine whether the task is behind or ahead of schedule, over or under budget. Task AC EV PV SV SPI Analysis CPI Analysis CV 8520 8000 4000 7500 3950 B 4600 5500 5860 5610 4 . BI U 2 Paragraph B @