Question: complete the table, and what is the difference between total float and free float A Problem-2 CD O EF GRI G C A D F
A Problem-2 CD O EF GRI G C A D F 6 5 2 7 3 8 1 9 10 12 11 13 16 14 18 17 15 Project completion time = 18 working days Critical Path: A, D, F, I, J. Activity A B E F G Total float 0 0 5 Free float 0 0 0 5 D 0 H 2 2 1 0 0 J 0 0