Question: Complete this exercise in MSProject. You can use your solution to the resources exercise (with the HR Manager available at 100%) as the basis for

Complete this exercise in MSProject. You can use your solution to the resources exercise (with the HR Manager available at 100%) as the basis for this exercise. Your project began on June 1 and it is now July 1. The progress and remaining time on each task is as follows: Task Elapsed Days of Work Days of Work Remaining A 2 0 B 8 0 4 0 D 10 4 E 0 8 F 0 6 G 0 3 I 0 6 Update the MSProject plan to reflect the progress and submit your file along with answers to the following questions: 1. What is the planned cost of completing the project 2. What is the schedule variance as of July 1? 3. What is the CPI as of July 1