Question: Complete this exercise in MSProject. Submit both your MSProject file and your answers to the questions below. You can use your solution to the scheduling
Complete this exercise in MSProject. Submit both your MSProject file and your answers to the questions below. You can use your solution to the scheduling exercise (before any tasks were crashed) as the basis for this exercise.
Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:
Task | Predecessor | Duration | Resource |
A | - | 2 | HR Manager |
B | - | 7 | HR Analyst |
C | A | 4 | HR Analyst |
D | B, C | 8 | HR Analyst |
E | D | 8 | Benefits Coordinator |
F | D | 6 | Benefits Coordinator |
G | E | 3 | HR Analyst |
H | E, F | 6 | HR Manager |
- Before adding resources, the project takes 29 days. Once resources constraints are entered and leveled, what is the total number of days to complete the project?
- According to the project statistics, what is the planned cost of the project?
- If the HR Manager is only available to work on the project 50% of the time, rather than dedicated to the project full-time, how many days will it take to complete the project?