Question: Complete this exercise in MSProject. Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource

Complete this exercise in MSProject.

Your project has three dedicated resources: HR Manager, costing $75/hour, HR Analyst, costing $25/hour, and Benefits Coordinator, costing $15/hour. Resource assignments are as shown:

Task

Predecessor

Duration

Resource

A

-

2

HR Manager

B

-

7

HR Analyst

C

A

4

HR Analyst

D

B, C

8

HR Analyst

E

D

8

Benefits Coordinator

F

D

6

Benefits Coordinator

G

E

3

HR Analyst

H

E, F

6

HR Manager

  1. Before adding resources, the project takes 29 days. Once resources constraints are entered and leveled, what is the total number of days to complete the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!