Question: Complete this table using the information below for the project AT THE END OF WEEK #4. Activity Percent Complete BCWS BCWP BCWP (using 50/50 Rule)
Complete this table using the information below for the project AT THE END OF WEEK #4.
| Activity | Percent Complete | BCWS | BCWP | BCWP (using 50/50 Rule) | ACWP | CV | SV | CV (using 50/50 Rule) | SV (using 50/50 Rule) |
| | | | | | | | | | |
| | | | | | | | | | |
| | | | | | | | | | |
| | | | | | | | | | |
| | | | | | | | | | |



000 mn (Time = weeks) PERCENT-COMPLETION REPORT Activity Date Started % Completed Time to Complete AC AD DE* BF 2/1 2/1 2/1 not started 2/14 100% 60% 100% www 40% 6 7 8 Total $ AB PROJECT PLANNING BUDGET: WEEKS AFTER GO-AHEAD Activity 1 2 3 4 5 2,000 2,000 2,000 AC 3,000 4,000 4,000 4,000 5,000 AD 2,000 3,000 2,500 BF 2,000 3,000 CE DE 3,500 3,500 EF Total 7.000 9.000 8,500 9,500 11,500 - 4,000 2,500 3,000 3,000 6,000 20,000 7,500 15,000 2,500 10,500 3,000 64,500 3,500 10,000 6,000 3,000 COST SUMMARY Week Ending Cumulative to Date Activity Budget Cost Actual (Over) Under Budget Cost Actual (Over) Under 4,000 AB AC AD BF DE 4.500 2,400 2,800 - (500) (2,400) (800) 3,500 6,000 15,000 7,500 2,000 3,500 6,200 12,500 7,400 4,500 (200) 2,500 100 (2,500) 3,500 2,000 3,500 Total 9,500 9,700 (200) 34,000 30,600 3,400 000 mn (Time = weeks) PERCENT-COMPLETION REPORT Activity Date Started % Completed Time to Complete AC AD DE* BF 2/1 2/1 2/1 not started 2/14 100% 60% 100% www 40% 6 7 8 Total $ AB PROJECT PLANNING BUDGET: WEEKS AFTER GO-AHEAD Activity 1 2 3 4 5 2,000 2,000 2,000 AC 3,000 4,000 4,000 4,000 5,000 AD 2,000 3,000 2,500 BF 2,000 3,000 CE DE 3,500 3,500 EF Total 7.000 9.000 8,500 9,500 11,500 - 4,000 2,500 3,000 3,000 6,000 20,000 7,500 15,000 2,500 10,500 3,000 64,500 3,500 10,000 6,000 3,000 COST SUMMARY Week Ending Cumulative to Date Activity Budget Cost Actual (Over) Under Budget Cost Actual (Over) Under 4,000 AB AC AD BF DE 4.500 2,400 2,800 - (500) (2,400) (800) 3,500 6,000 15,000 7,500 2,000 3,500 6,200 12,500 7,400 4,500 (200) 2,500 100 (2,500) 3,500 2,000 3,500 Total 9,500 9,700 (200) 34,000 30,600 3,400