Question: Compute process Cycle Time (CT) for the following business process: CT - 1 day CT - 2 days PT = 3 hrs CT - 3

 Compute process Cycle Time (CT) for the following business process: CT

Compute process Cycle Time (CT) for the following business process: CT - 1 day CT - 2 days PT = 3 hrs CT - 3 days PT = 0.5 hrs PT - 2 hrs 0.35 X 0.65 8.6 7.05 CO 6.05