Conider the project schedule shown in the table below. Times are given in days. Predecessor(s) ES LS LF Duration 2 Slack 0 0 EF 2 10 Activity A B 0 A A 2 10 8 5 2 D 4 6 B B, C C 10 10 14 15 16 10 5 E F 0 15 15 7 1 8 15 G E, F 5 15 20 0 What is the duration of activity B? The duration of activity B is days. What is the project duration? The project duration is days. What is the critical path? (Enter your answer as a sequence of capital letters with no dashes or spaces.) The critical path is