Question: Conider the project schedule shown in the table below. Times are given in days Predecessor(s) Duration ES EF LS LA Slack 0 0 1 0

Conider the project schedule shown in the table

Conider the project schedule shown in the table below. Times are given in days Predecessor(s) Duration ES EF LS LA Slack 0 0 1 0 Activity B C 1 2 3 3 2 1 2 D 5 A A B B, C E. F 9 0 8 3 11 11 E F G 11 3 6 11 11 3 5 5 11 16 0 What is the EF time for activity F? The EF time for activity F is days. What is the project duration? The project duration is days What are the critical activities? (Enter your answer as a sequence of capital letters with no dashes or spaces.) The critical activities are