Question: Consider a project that has been modeled as follows: table [ [ Activity , Immediate Predecessors,Optimistic,Most Probable,Pessimistic ] , [ A , - -

Consider a project that has been modeled as follows:
\table[[Activity,Immediate Predecessors,Optimistic,Most Probable,Pessimistic],[A,--,2,5,8],[B,--,2,3,7],[C,--,5,7,9],[D,A,7,12,14],[E,A,3,4,5],[F,A, B,6,9,12],[G,C,4,6,8],[H,C,4,6,8],[I,E,F,G,5,6,12],[J,H,12,7,14]]
How many days should I give myself to ensure a 95% probability of completing?
28.56
32.20
30.73
33.85
 Consider a project that has been modeled as follows: \table[[Activity,Immediate Predecessors,Optimistic,Most

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!