Question: Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 2 5 8 2 3 7 5 9

Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 2 5 8 2 3 7 5 9 A 7 A, B C C E,F.G 5 12 H 12 14 K DIJJ 4 What is the probability it takes longer then 30 ? O .22 O .83 O .17 O .12
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
