Question: Consider a project that has been modeled as follows: table [ [ Activity , Immediate Predecessors,Optimistic,Most Probable,Pessimistic ] , [ A , - -

Consider a project that has been modeled as follows:
\table[[Activity,Immediate Predecessors,Optimistic,Most Probable,Pessimistic],[A,--,2,5,8],[B,--,2,3,7],[C,--,5,7,9],[D,A,7,12,14],[E,A,3,4,5],[F,A, B,6,9,12],[G,C,4,6,8],[H,C,4,6,8],[I,E,F,G,5,7,12],[J,H,12,13,14],[K,D,I,J,2,3,4]]
What is the expected completion time?
 Consider a project that has been modeled as follows: \table[[Activity,Immediate Predecessors,Optimistic,Most