Question: Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 2 5 8 B 2 3 7 C

Consider a project that has been modeled as

Consider a project that has been modeled as follows: Activity Immediate Predecessors Optimistic Most Probable Pessimistic A 2 5 8 B 2 3 7 C 5 7 9 D A 7 12 14 E A 3 4 5 F A, B 6 9 12 G 4 6 8 H C 4 6 8 I E,F,G 5 7 12 J 12 13 14 K D,I,J 2 3 4 How many days should I give myself to ensure a 95% probability of completing? 028.56 O 32.20 0 33.85 O 30.73