Question: Consider a project where the optimistic, most likely, and pessimistic time estimates are 6 , 1 2 , and 3 0 days, respectively. If unforeseen
Consider a project where the optimistic, most likely, and pessimistic time estimates are and days, respectively. If unforeseen risks increase the pessimistic estimate by how does this impact the expected duration of the task?
Increases by days
Increases by days
Increases by days
Increases by days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
