Question: Consider a project where the optimistic, most likely, and pessimistic time estimates are 6 , 1 2 , and 3 0 days, respectively. If unforeseen

Consider a project where the optimistic, most likely, and pessimistic time estimates are 6,12, and 30 days, respectively. If unforeseen risks increase the pessimistic estimate by 50%, how does this impact the expected duration of the task?
Increases by 10 days
Increases by 4 days
Increases by 8 days
Increases by 6 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!