Question: Consider a project whose activities are listed in the table below. What is the critical path of the project? Activity Immediate Predecessors Duration (days) A
Consider a project whose activities are listed in the table below. What is the critical path of the project?
| Activity | Immediate Predecessors | Duration (days) |
| A | None | 5 |
| B | None | 4 |
| C | A | 4 |
| D | A | 2 |
| E | B | 3 |
| F | C | 6 |
| G | D, E | 5 |
| a. | ACF | |
| b. | ADG | |
| c. | BEG | |
| d. | There are multiple critical paths. |