Question: constraint management Consider a project whose activities are listed in the table below. Activity F will have slack time as long as Activity Immediate Predecessors
Consider a project whose activities are listed in the table below. Activity F will have slack time as long as Activity Immediate Predecessors None B None C AB D C E F D G F a Duration of F Duration of G Oc Duration of D+Duration of F> Duration of E Duration of G Od Duration of D+Duration of F